Haileybury: City Stage 1

 

Sector: Education

Address: 383 King Street, Melbourne

Client : Haileybury

Client PM : Gallagher Jeffs

Final($) : 6.2m

Duration : 20 Weeks

Completed : April 2016

Architect : Darren Cartnell Architects

 
Harris HMC were engaged by Haileybury to complete Stage 1 of their new City Campus site, including an internal and external refurbishment of an existing office building, converting it into a private school complex including:

  • Structural works included building an external staircase, internal disabled ramp, and a new entrance to the carpark
  • Upper Basement: Store room area, line marking for new student drop off zone, additional bike racks
  • Ground Floor: Auditorium, student hub, medical centre, study area, refurbishment of toilets and existing lift lobby area
  • 1st Floor: Junior school activity area, refurbishment of existing toilets, gym facilities, staff work room, staff related offices
  • 3rd Floor: Early Learning Centre, transformation of the level 3 balcony into an outdoor landscaped terrace and playground with shade structure, staff related offices, 6 junior class rooms, computer lab, and break out area
  • Base Build Services Upgrade: Electrical, communication, security, fire, hydraulic services, mechanical
  • Fa├žade: Repaving forecourt, Facade treatment and signage